General construction update: 8 October 2021

Over the next few weeks, we will continue the concrete pours for levels 8 and 9 of the new building. We anticipate level 9 will be completed by 25 October 2021.

The concrete pouring will take place within the standard site hours of 8am to 6pm (please note: construction staff are allowed on site from 7.30am to undertake non-noisy works). If there are any planned works that need to be completed outside of these hours, we will inform our neighbours in advance. 

Piling will also continue for the bridge linking the Paterson building with the existing Christie site – these works may cause some noise or vibration, and we will work to minimise any impact on our neighbours.

Work to install the electrical and plumbing systems is ongoing throughout the building, while plastering of the internal walls is continuing. 

The glass walls to the outside of the building are being installed on both sides of the building. This work is due to take several months. Pedestrian access routes will be affected, with pedestrian diversions in place on Wilmslow Road.

Latest CGI images of the Paterson building, courtesy of Arcadis

  • slider image
    Picture credit: Arcadis
  • slider image
    Picture credit: Arcadis
  • slider image
    Picture credit: Arcadis
Previous Next

You can see how the building project is progressing in this video from October 2021.

How do I find out more?

Our community relations team will be sending out fortnightly updates about the construction work at The Christie. If you’d like to receive the updates via email or text, you can contact the team:

Last updated: October 2021